PROJECT AUTHORIZATION PACKET ID: PMT-NVKM
CONTRACT ID EMARS PROGRAM CODE AUTHORIZATION NO:
6898802R      68988 11
It is hereby ordered that the project herein described be undertaken and accomplished within the funding level authorized.
PROJECT ID PROJECT ID NUMBER FEDERAL PROJECT NUMBER 6 YR PLAN ITEM NUMBER 6 YR PLAN ITEM PARENT NUMBER




01-00330 1-.-
PROJECT TYPE PROJECT LENGTH NUMBER OF BRIDGES SYSTEMS
NEW ROUTE 3.3000 MI
PROJECT PHASE
&
RESPONSIBILITY
PLANNING DESIGN RIGHT OF WAY UTILITIES
DOH
CONSTRUCTION TITLE DEEDED TO: MAINTENANCE OTHER
FUNDING & TIME
ACCOUNTABILITY
PARTICIPATING AGENCIES
FEDERAL STATE DOH LOCAL OTHER
REQUESTED FUNDS FOR THIS AUTHORIZATION
ITEM NUMBER PHASE FUND PROGRAM FEDERAL FISCAL YEAR STATE FISCAL YEAR
FEDERAL APPR
CODE
CURRENT FUNDING REQUEST
1-330 R 1100 FD04 2020 ($189,787.51)
CURRENT FUNDING REQUEST TOTAL: ($189,787.51)
AUTHORIZATION SUMMARY FOR THIS 10-1 SERIES
PHASE TOTAL AUTHORIZATION TO DATE (INCL. CURRENT REQUEST)
PLANNING $0.00
DESIGN $1,350,000.00
UTILITIES $150,000.00
R/W $6,091,212.49
CONSTRUCTION $0.00
NON-HIGHWAYS $0.00
  Total: $7,591,212.49
REMARKS: RELEASE $189,787.51 OF FD04 FUNDS FROM 6898802R. SAC
 
Project Approval Recommended By:
Andy Barber   4/13/2020
Signed and Approved by:
Jim Gray   4/14/2020
AUTHORIZATION LOCATION
ITEM NO. COUNTY DIST FACILITY NAME
ROUTE LENGTH SCOPE
01-00330.00 LIVINGSTON


1 PADUCAH - SMITHLAND US 60 3.3000 MI RELOCATION OF US-60 FROM APPROX. 0.8 MILE EAST OF THE TENNESSEE RIVER BRIDGE TO 0.5 MILE EAST OF RUDD-SPEES ROAD AT LEDBETTER.